Formulas For Work And Time
Formulas for work and time
Work: When the certain amount of job is assigned to an individual known as Work
Time: Time is defined as the required duration to complete the task.


Work and Time Formula's
Definition
- Work: In terms of mathematics work is defined as the amount of job assigned or the amount of job actually done.
- Time: Time is defined as the number of days or hours required to complete the task
Formula's for Work and Time
Work from Days:
If A can do a piece of work in n days, then A’s one day work = n1​
Days from work:
If A’s one day work = n1​, then A can finish the work in n days
Work Done by A and B
A and B can do a piece of work in ‘a’ days and ‘b’ days respectively.
When working together they will take a+bab​ days to finish the work
In one day, they will finish (aba+b​)th part of work.
Ratio:
If A is thrice as good a workman as B, then:
Ratio of work done by A and B = 3: 1.
Ratio of times taken by A and B to finish a work = 1: 3
Efficiency:
Efficiency is inversely proportional to the
Time taken when the amount of work done is constant.
Efficiency α = Time Taken1​
Basic Rules for Work and Time
Rule 1: If A completes a piece of work in x days. And B can completes same piece of work in y days .
Then,
One day work of A = x1​ One day work of B = y1​
Work done by A + B = x1​ + y1​ = xyx+y​
Total time = x+yxy​
Rule 2: If A completes a piece of work in x days. B completes same piece of work in y days .C completes same piece of work in z days
Then,
One day work of A = x1​
One day work of B = y1​
One day work of C = z1​
Work done by A + B + C = x1​ + y1​ + z1​ = xyzyz+xz+xy​
Total time = xy+yz+zxxyz​.
Rule 3: If M1 men can complete a work W1 in D1 days and M2 men can complete a work W2 in D2 days then, W1​M1​D1​​ = W2​M2​D2​​ .
If Time required by Both M1 and M2 is T1 and T2 respectively, then relation is W1​M1​D1​T1​​ = W2​M2​D2​T2​​
Rule 4: If A alone can complete a certain work in ‘x’ days and A and B together can do the same amount of work in ‘y’ days,
Work done by b =1/y – 1/x = x-y/xy
Then B alone can do the same work in xy/(x-y)
Rule 5: If A and B can do work in ‘x’ days.
If B and C can do work in ‘y’ days.
If C and A can do work in ‘z’ days.
Work done by A,B and C = ½ *(1/x+1/y+1/z)
Total time taken when A, B, and C work together xyz/(xy + yz + zx)
Rule 6: Work of one day = Total number of working daysTotal work​
Total work = one day work × Total number of working days
Remaining work = 1 – work done
Work done by A = A’s one day work × Total number of working days of A
Rule 7:If A can finish nm​ part of the work in D days.
Then total time taken to finish the work by A = nm​D​ = mn​ × D days
Rule 8:
If A can do a work in ‘x’ days
B can do the same work in ‘y’ days
When they started working together, B left the work ‘m’ days before completion then total time taken to complete the work = (y+m)x/x+y
Rule 9: A and B finish work in a days.
They work together for ‘b days and then A or B left the work.
B or A finished the rest of the work in ‘d’ days.
Total time taken by A or B alone to complete the work = a–bad​ or a−bbd​
Work and Time Formulas & Three Universal Rules
- If M1 persons can do W1 work in D1 days and M2 persons can do W2 works in D2 days then the formula W1​M1​D1​​ = W2​M2​D2​​ .It can be written as M1D1W2 = M2D2W1.
- If the persons work T1 and T2 hours per day respectively W1​M1​D1​T1​​ = W2​M2​D2​T2​​
- It can be written as, M1D1 T1 W2 = M2D2 T2W1
- If the persons has efficiency of E1 and E2 respectively then W1​M1​D1​T1​E1​​ = W2​M2​D2​T2​E2​​ Therefore, M1D1T1E1W2 = M2D2T2E2W1.
In all the above formula,
M = Number of workers
D = Number of days
T = Time required
W = Units of work
E = Efficiency of workers
Read Also – Tips & tricks to solve work and time questions








